Hi everyone,
About time for an update! We had another meeting with the architect on December 22nd. Over the last few months he has been working with the engineer, drawing up structural, plumbing and electrical plans, and made a few minor changes to the floor plan to account for these. We also went through the glazing schedule, confirming the sizes and types of all the windows. We also met the builder for the first time!

Latest plan revisions:





There were another 20 or so diagrams/plans with these ones but I won't upload them all - things like updated elevation diagrams, subfloor plan, roof plan, and so on, I won't scan them all :)

Major changes:

- A niche running all the way around the top cornice area of 3 sides of the house - this was because the roof support structure needed a bit more space than what was available (and raising the roof level would have required going back to planning approval) so to keep window sizes the standard height they added a gap. This works out well because it provides a spot where blinds etc. can be installed and then be hidden when they are open - and also allows some niches to be built into some walls.

- Laundry chute location confirmed, after about 4 different options were attempted!

- AV/network cabinet location changed - made it bigger and placed it between the theatre and the garage. Discussions with many AV enthusiasts have let me to believe that cat5/6 will be used for AV in the future (there are adaptors to do so now) so as a result it made sense to consolidate the network and AV runs.

- A step before entering the garage - because the garage is 300mm higher than the rest of the lower floor. I think the step may get in the way a bit, so will raise some alternatives with the architect!
We've also confirmed some floor surfaces:

- Polished concrete in the downstairs hallway (as well as hopefully a polished concrete benchtop)

- Modwood for the decks - modwood is made of sawdust and recycled plastic milk bottles, doesn't require oiling every year or other maintenace, and doesn't splinter!
I've also done some sketchup mockups of some areas to give the architect and builder an idea of what we are after.
Kitchen:





(Appliances are Electrolux oven & induction cooktop, F&P fridge, Robinhood rangehood and Asko dishwasher)

Laundry:




And my work of art, the AV unit!


Construction is now expected to start in March 2011.. which means we may not be in there before Christmas 2011 as we had hoped, but that's ok, we'd rather it be done well than done quick!
 
That'll do for now, electrical and plumbing to come in a future update!